HOUSTON - CyrusOne's third data center (514,000 sf) is underway at its 45-acre Houston West campus at 4201 Southwest Fwy. along Beltway 8.

Upon completion, the new facility will include 428,000 sf of raised floor capacity, 86,000 sf of Class A office space, and up to 96 megawatts of critical load. The third facility serves to increase data center capacity available at the Houston West campus to more than 1 million sf.

The company plans to construct the third facility in two phases, with Phase 1 consisting of a 321,000-sf powered shell with 214,000 sf of raised floor space, 43,000 sf of Class A office space and up to 48 megawatts of critical power load. It expects the first data hall, which will have approximately 54,000 sf of raised floor, to be operational by early 2015.

Read more at the Wall Street Journal.