383K-sf industrial project underway along SH 6

​HOUSTON – Construction is underway on Houston Point 290, a 27.2-acre industrial park that will have three 32-ft clear-height warehouse buildings:Building A at 9320 SH 6 will be 149,918 sf with 210-ft...
Fallback Image
by
Community Impact Newspaper

​HOUSTON – Construction is underway on Houston Point 290, a 27.2-acre industrial park that will have three 32-ft clear-height warehouse buildings:

  • Building A at 9320 SH 6 will be 149,918 sf with 210-ft building depth, 31 dock doors, 185-ft truck court, 30 trailer spots, and166 parking spaces;
  • Building B at 9310 SH 6 will be 106,187 sf with 145-ft building depth, 42 dock doors, 185-ft truck court, and 175 parking spaces; and 
  • Building C at 9302 SH 6 will be 126,971 sf with 170-ft depth, 38 dock doors, and 99 parking spaces.

Construction is slated to wrap up in the fourth quarter of this year.​​​​

Fallback Image
Written by
Community Impact Newspaper
Last updated
Mar 28, 2024

In This Article

You might also like

TG Magazine
PUBLISHED SINCE 1977

TG Magazine

Check out the latest issue of our flagship publication.

SUBSCRIBE TO OUR

Publications

Receive our economic and housing reports and newsletters for free.