Bundles and bundles of energy to the Panhandle
AMARILLO – Xcel Energy has completed a $7.6 million upgrade to the Soncy Substation at the intersection of W. I-40 and Coulter St.
The upgrades allow the company to deliver more electricity to the area while improving the reliability of the system.
A new 115-kilovolt line was built to provide the power source for the substation, improving the station’s capacity to deliver more electricity onto lower-voltage distribution lines from the facility. A new distribution feeder line was also added to relieve high loading on the existing lines.
Xcel is planning other improvement projects in the area over the next five years, including:
a new transformer and additional feeder lines for the Hillside Substation, which is near capacity due to the surrounding residential and commercial growth;
voltage conversions in northeast Amarillo that will provide options to reroute power in the event of overloading or storm damage;
capacity upgrades to existing substations serving east and southeast Amarillo;
a relocation and upgrade of feeder lines that allows for the widening of Loop 335 in south Amarillo and paves the way for additional load growth;
a new substation and feeder lines in the Preston West development to serve growing residential and commercial demand; and
a new substation and feeder lines in the Hunsley Hills area in north Canyon to serve recent and planned residential expansion.