​​The Frost Tower under construction.SAN ANTONIO – The $142 million, 23-story Frost Tower at 111 W. Houston St. is past its halfway point.

Working under a spring 2019 deadline, crews have built 19 of the 23 floors, and subcontractors have started placing the exterior glass.

The Frost Tower is expected to be topped out by middle or late June 2018.

The project represents the first new high-rise office in downtown San Antonio in nearly three decades—adding more than 400,000 sf of retail and office space.
San Antonio Business Journal
San Antonio-New Braunfels
Office
https://www.bizjournals.com/sanantonio/news/2018/04/19/frost-tower-construction-reaches-new-milestone.html